Dear Red River Community,
We’re pleased to announce upcoming construction projects aimed at enhancing the infrastructure and safety of Red River. Please find project details below:
- Main Street Project
- South side: Completing items delayed last year due to weather.
- North side: Starting at Jayhawk Road intersection, progressing approximately one block every 2–3 weeks.
- High Street Project
- Utility work begins with the storm drain system from Center Court to Jacks and Sixes.
- Concrete and asphalt work will follow from NM Highway 38 to Center Court after utility completion.
- Tenderfoot Area
- Work begins today, April 28, 2025, with potholing and main water line installation at Tenderfoot Court.
- Schedule updates will be posted regularly.
Thank you for your understanding and patience as we work to improve our town!